The 2019 voter-approved Library Levy provided $13.8 million in funding to seismically retrofit the historic Green Lake, University and Columbia branches.
A survey identified the three unreinforced Carnegie buildings as high-risk for damage and loss of life in the event of a major earthquake. The 2016 survey was conducted by the city Department of Construction and Inspection, which advised these buildings be retrofitted in the next seven years.
The seismic upgrade to each of these landmarked buildings is estimated to take approximately 18 months to complete. The buildings will be closed during construction.
Detailed information on each project, including building closure dates and alternative services, will be shared as it becomes available.
The Seattle Public Library’s Green Lake Branch, one of the Library’s historic Carnegie buildings, reopened on October 28, 2024. The branch temporarily closed beginning February 1, 2023 for major renovations, including a seismic retrofit and the installation of an electric HVAC system and accessible elevator, and other interior improvements.
This project, funded by the 2019 Library Levy, presented a unique opportunity to make the Green Lake Branch safer, greener, and better able to meet the needs of the community while preserving its important legacy.
The improvements and renovations to the Green Lake Branch included:
The Seattle Public Library’s University Branch will temporarily close from Wednesday, January 29, until late 2026 for a seismic retrofit and other major renovations, including the installation of an electric HVAC system, an elevator, additional restrooms, study rooms, and a dedicated multipurpose room.
Project details, plans and illustrations may be found in the University Branch Presentation Boards and Architectural Plans. The unique historical and cultural legacy of the University Branch will be protected and preserved throughout the project.
These major renovations to the University Branch are funded by the 2019 Library Levy and by FEMA’s Hazard Mitigation and Legislative Pre-Disaster Mitigation Grant Programs.
Project Scope:
Seismic Retrofit
The University Branch will undergo a seismic retrofit to protect patrons, staff and the building during an earthquake.
HVAC Installation
The current gas-powered furnace will be replaced with a modern, electric HVAC system, providing air conditioning and improved ventilation while reducing carbon emissions.
Accessibility Improvements
Access to the branch will be improved with new accessible ramps and paths from perimeter sidewalks to branch entrances, new accessible entrances at the southwest corner and north side of the branch, new accessible parking spaces, new accessible restrooms on both floors and the installation of branch elevator.
Interior Renovations
The branch interior will be reconfigured with the addition of two new study rooms, a dedicated music room, a relocated and renovated meeting room and additional public restrooms. New and improved lighting, shelving, carpets and furniture will also be installed in the branch.
Exterior Renovations
The branch exterior will be repaired and repainted. Historic design elements, including exterior windows and stucco will be restored and weatherproofed. The existing clay tile roof will be retained with minor repairs.
Sustainability
The renovated branch will meet the City of Seattle’s goals for environmentally responsible design and will be LEED Gold Certified. Along with other energy conservation improvements, the branch will be outfitted with solar panels on the roof and capacity for future EV charging stations on the parking lot.
The project design was approved by the Landmarks Preservation Board in September 2024.
The project went out to bid in November 2024 and contractors and subcontractors will be selected before the end of the year. SHKS architects is the architectural firm designing and overseeing the project.
The University Branch will close from Wednesday, January 29, 2025, until late 2026 while this project is underway.
With funding from the 2019 Library Levy, the Columbia Branch will undergo major renovations projected to begin late 2026 or early 2027. The work will include a seismic retrofit, the installation of an electric HVAC system, extensive accessibility improvements and interior modernization. The unique historical and cultural legacy of the Columbia Branch will be protected and preserved throughout the project. We expect the Columbia Branch project to be similar in scope to the Green Lake Branch project that was successfully completed in October 2024.
Early project scope and design work for the Columbia Branch project is complete. In June 2024, we received funding for the installation of a modern HVAC system at five Library locations, including the Columbia Branch, through FEMA’s Hazard Mitigation Grant Program. We do not yet have an anticipated start date for construction.